Introduction
PMP exam having vast knowledge shearing exam which allow students to develop the vital skill set to enhance the project management expertise in very limited time, but to understand the same you might require the PMP Exam Dictionary to solve and understand the terms and its importance.
The PMP Exam Dictionary will help you alphabetically to understand the important and meaning of each PMP exam domain key elements as provided below.
PMP Dictionary
A
- Acceptance
Criteria: Conditions that a project deliverable must meet to be
accepted by stakeholders or the customer. These criteria are often defined
in the project scope and quality management plans and serve as a basis for
validating the project’s deliverables. - Example:
For a software development project, acceptance criteria might include
functional features, compatibility, and performance standards that the
software must meet before being handed over to the client. - Activity:
A specific task or group of tasks required to complete a project
deliverable. Activities consume time and resources. - Example:
In a construction project, activities could include “installing
electrical wiring” or “pouring the foundation.” - Activity
List: A comprehensive list of all activities required to complete the
project. It’s used in project planning to ensure that nothing is missed. - Example:
In the project of building a website, activities would include
“designing the homepage,” “coding the backend,” and
“conducting usability testing.” - Activity
Duration: The total time required to complete a specific activity,
usually measured in hours, days, or weeks. - Example:
The activity “writing code” might have a duration of 10 days. - Agile:
A methodology that emphasizes flexibility, collaboration, and iterative
progress, especially in environments where project requirements evolve or
are not fully known at the start. - Example:
Agile is often used in software development, where the product evolves
through successive iterations (called sprints). - Alternative
Analysis: A decision-making technique used to evaluate various options
for solving a project problem or challenge. It involves comparing the
advantages and disadvantages of multiple alternatives. - Example:
Deciding whether to build a product in-house or outsource it to a vendor.
The analysis considers cost, quality, and timeline. - Assumption
Log: A document that records assumptions made during project planning,
including those about resources, risks, and external factors. - Example:
An assumption might be that a supplier will deliver materials on time or
that project stakeholders will provide timely feedback.
B
- Baseline:
A fixed reference point against which project performance is measured. It
includes the scope baseline, schedule baseline, and cost baseline. - Example:
The schedule baseline includes the planned start and finish dates for all
tasks, serving as a comparison point against the actual project
performance. - Benefits
Management Plan: A plan outlining how the project will deliver value
to stakeholders, measuring its success, and tracking benefits over time. - Example:
In a project aimed at increasing efficiency in manufacturing, the
benefits management plan would track the reduction in production time or
cost savings achieved after the project. - Benchmarking:
The process of comparing project performance or processes against the best
practices or standards in the industry or within the organization. - Example:
A company may benchmark its project completion times against other
companies in the same sector to identify areas for improvement. - Brainstorming:
A technique used in group settings to generate a variety of ideas,
solutions, or approaches to a problem. - Example:
During risk identification, the team might brainstorm potential risks
associated with a product launch, such as supply chain disruptions,
regulatory issues, and market competition.
C
- Change
Control: The process of managing and controlling changes to the
project scope, schedule, and costs. - Example:
A client requests a change to the scope of a project by adding a new
feature. Change control would ensure that the change is evaluated,
documented, and its impact on time and cost is assessed before it is
approved. - Change
Control Board (CCB): A group of stakeholders responsible for
reviewing, evaluating, and approving or rejecting changes to the project’s
baseline. - Example:
The CCB might consist of the project manager, senior managers, and key
stakeholders who meet to evaluate any proposed changes. - Change
Request: A formal proposal to modify any aspect of the project,
including scope, schedule, or resources. - Example:
If a client requests a scope change, they would submit a change request,
which would be evaluated by the project manager and other relevant
stakeholders. - Communication
Management Plan: A plan that outlines how project information will be
communicated to stakeholders, ensuring timely, appropriate, and effective
communication. - Example:
The plan might specify that weekly status reports will be sent to the
project sponsor, and daily stand-up meetings will occur for the project
team. - Constrained
Optimization Method: A mathematical method used to optimize project
performance while meeting various constraints, such as time, resources, or
budget. - Example:
It may be used in resource leveling to determine the best way to allocate
resources across project tasks while minimizing the overall project
duration. - Contingency
Plan: A predefined set of actions designed to address potential risks
or unforeseen events that may impact the project. - Example:
In case of a supply chain disruption, a contingency plan might involve
using an alternative supplier to avoid project delays. - Cost
Baseline: The approved version of the project budget, excluding
management reserves. It serves as a benchmark for measuring project cost
performance. - Example:
The project budget is $1 million, and the cost baseline would include
detailed allocations for labor, materials, and equipment. - Cost
Management Plan: A plan that describes how costs will be managed,
controlled, and tracked during the project. - Example:
It may outline how project expenses will be recorded, how cost variances
will be handled, and what steps will be taken to keep the project within
budget.
D
- Data
Analysis: The process of evaluating project data to identify trends,
patterns, and insights that inform decision-making. - Example:
Using data analysis to track progress and determine if a project is on
schedule or if delays are occurring. - Decision
Tree Analysis: A graphical decision-making tool used to evaluate
potential outcomes of different actions based on their likelihood and
impact. - Example:
A decision tree may be used to decide whether to proceed with an
expensive risk mitigation strategy or accept a certain risk. - Deliverable:
A specific, measurable output of the project, which can be a product,
service, or result. - Example:
A deliverable could be a finished building, a completed software module,
or a final report. - Dependency:
The relationship between project activities that determines the order in
which they must be performed. Dependencies are usually categorized as
finish-to-start, start-to-start, finish-to-finish, or start-to-finish. - Example:
A finish-to-start dependency exists when Task B cannot begin until Task A
is completed. - Develop
Project Charter: The process of creating a formal document that
authorizes the project, defines the project objectives, and assigns
responsibility. - Example:
The project charter would include the project’s purpose, goals,
high-level scope, and the project manager’s authority. - Develop
Project Management Plan: The process of developing a comprehensive
plan to guide the execution, monitoring, and control of the project. - Example:
This includes integrating plans for scope, schedule, cost, quality, human
resources, communications, and risk into a unified document.
E
- Earned
Value Management (EVM): A technique for measuring project performance
by comparing the planned progress (PV), actual progress (EV), and the cost
incurred (AC). EVM helps assess cost and schedule performance. - Example:
If the project is 60% complete and has spent 50% of the budget, the
project is on budget but might be behind schedule. - Effort:
The amount of labor required to complete a specific task, usually measured
in person-hours or person-days. - Example:
Writing code for a software application might require 200 person-hours of
effort. - Estimate
Activity Durations: The process of approximating the time required to
complete each project activity. - Example:
Estimating the time required to complete a task like “testing the
software” could result in an estimate of 5 days. - Estimate
Costs: The process of approximating the financial resources required
to complete project activities. - Example:
Estimating the cost of materials, labor, and equipment needed to finish a
construction project.
F
- Fast
Tracking: A technique used to shorten the project schedule by
performing tasks in parallel that would normally be done sequentially. - Example:
If a project has tasks that can be overlapped (such as starting
construction before the design phase is entirely complete), fast tracking
can reduce project duration. - Forecasting:
The process of predicting future project performance based on current
progress and trends. - Example:
A project manager might forecast that the project will be delayed based
on current progress and historical performance data.
G
- Governance:
The systems, processes, and policies that guide the decision-making
process within an organization or project. - Example:
An organization might have governance standards for project approval,
reporting, and change management.
H
- Human
Resource Management Plan: A document that outlines how human resources
will be managed throughout the project. It includes team roles,
responsibilities, and how the project team will be developed and
evaluated. - Example:
The plan might specify how new team members will be onboarded, how
performance will be assessed, and what skills development opportunities
will be available. - Human
Resource Planning: The process of identifying and documenting project
roles, responsibilities, and required skills to ensure that the necessary
human resources are available for the project. - Example:
Determining the need for a project manager, designers, and developers for
a software project and defining their respective roles.
I
- Integrated
Change Control: A process used to evaluate and manage changes across
the entire project to ensure that any change to the scope, schedule, or
costs is reviewed, approved, and documented. - Example:
If a client requests a change in the project’s requirements, the change
would be evaluated through integrated change control to assess its impact
on the project’s scope, cost, and schedule. - Issue
Log: A document used to record and track issues that arise during the
project. It helps the project team manage and resolve issues in a timely
manner. - Example:
An issue log might include a delayed delivery from a supplier, which is
being tracked to ensure resolution. - Iterative
Process: A process that repeats phases or activities until a desired
outcome is achieved. This is common in Agile methodologies where work is
done in sprints or iterations. - Example:
In software development, iterative processes involve developing the
software in small chunks, with each iteration resulting in a potentially
shippable product. - Lessons
Learned: Knowledge gained from the performance of a project that can
be used to improve future project planning and execution. - Example:
If a project experienced frequent scope changes, lessons learned might
include a recommendation to implement a more robust scope change control
process in the next project. - Management
Reserve: A portion of the project budget or time that is set aside for
unforeseen changes or risks that may arise during the project. - Example:
A project might set aside 10% of the total budget as a management reserve
to deal with unplanned costs or scope changes.
J
- Just-in-Time
(JIT): A production strategy that aims to reduce waste by receiving
goods only when they are needed in the production process, thereby
reducing inventory costs. - Example:
A construction company may use JIT principles to ensure that materials
are delivered just before they are needed on-site, reducing storage
costs.
K
- Kick-off
Meeting: A meeting held at the beginning of the project to align
stakeholders, the project team, and any other relevant parties on the
project’s objectives, roles, and plans. - Example:
During the kick-off meeting, the project manager presents the scope,
schedule, and key deliverables of the project to ensure everyone
understands the project’s goals and objectives.
L
- Lag:
A delay between two project activities, typically applied to schedule
dependencies. For example, there might be a lag time between the
completion of a design and the start of construction to allow time for
review. - Example:
A finish-to-start relationship might include a 2-day lag before the next
task can start. - Lead:
The amount of time that a dependent task can overlap with the preceding
task. It allows for tasks to be performed simultaneously. - Example:
In a construction project, the preparation of the foundation could
overlap with the delivery of materials for the next phase, provided the
materials are ready ahead of time. - Lessons
Learned Register: A tool used to document and share knowledge acquired
during the project. It is updated regularly to capture insights and can be
referenced for future projects. - Example:
After a project concludes, the lessons learned register might include the
importance of having clear requirements from the start to avoid scope
creep.
M
- Matrix
Structure: An organizational structure that blends functional and
projectized structures. Project team members report to both a functional
manager and a project manager. - Example:
In a matrix structure, a software developer might report both to the IT
department manager and the project manager responsible for a specific
software development project. - Monte
Carlo Simulation: A quantitative risk analysis technique used to model
the probability of different outcomes in a project by running simulations
of possible scenarios. - Example:
In a construction project, Monte Carlo simulation might be used to
predict the likelihood of completing the project on time, considering
potential delays and cost overruns. - Monitoring
and Controlling Process Group: A process group that involves tracking,
reviewing, and regulating the progress and performance of the project,
identifying any areas where changes are needed, and ensuring that project
objectives are being met. - Example:
During the project execution phase, monitoring and controlling processes
ensure that the project is on track and that any issues are addressed
promptly.
N
- Net
Present Value (NPV): A financial metric used to evaluate the
profitability of a project by calculating the difference between the
present value of cash inflows and the present value of cash outflows over
a project’s lifetime. - Example:
A project that is expected to generate $500,000 annually for 5 years
might be evaluated using NPV to determine whether its expected return
justifies the initial investment. - Non-Disclosure
Agreement (NDA): A legal contract that protects confidential
information shared between parties during the project. It ensures that
sensitive information is not disclosed to unauthorized individuals. - Example:
A software company might require an NDA before sharing proprietary code
or design details with a third-party developer.
O
- Objectives:
The specific, measurable outcomes or goals that a project aims to achieve.
Objectives are typically aligned with stakeholder expectations and
business goals. - Example:
The objective of a website development project might be to create a fully
functional e-commerce platform with an integrated payment gateway within
6 months. - Opportunity:
A positive risk or situation that, if leveraged, can benefit the project.
Opportunities are typically part of the risk management process. - Example:
A new technology might provide an opportunity to speed up the project or
reduce costs, which is identified and explored as part of the project’s
risk response planning. - Organizational
Process Assets (OPA): The company’s policies, procedures, templates,
historical information, and knowledge bases that are used to manage the
project. - Example:
An organization may have an OPA that includes risk management templates
and a lessons learned database that can help streamline project
execution.
P
- Payback
Period: The amount of time required for the investment in a project to
repay its original cost from the project’s cash inflows. - Example:
If a project costs $200,000 and is expected to generate $50,000 in
revenue per year, the payback period would be 4 years. - Perform
Integrated Change Control: A process of reviewing and managing changes
across the project, ensuring they are aligned with the project’s goals and
objectives. - Example:
If a project manager proposes a scope change, it will go through
integrated change control, where the impact on the budget, schedule, and
resources will be analyzed. - Procurement
Management Plan: A plan that outlines how procurement processes will
be handled, including vendor selection, contracts, and performance
monitoring. - Example:
In a construction project, the procurement management plan might include
the strategy for acquiring building materials and subcontractors for
various tasks. - Project
Charter: A formal document that officially authorizes the project,
outlines its objectives, and gives the project manager the authority to
allocate resources and start work. - Example:
A project charter for a website development project would define the
scope, budget, and schedule, and authorize the project team to begin
development.
Q
- Quality
Assurance (QA): A proactive process of auditing and reviewing the
project processes to ensure quality standards are being met and that the
project is on track to deliver the desired outcomes. - Example:
A quality assurance team might conduct regular audits on the
manufacturing process to ensure that products meet the required quality
standards. - Quality
Control (QC): The process of monitoring and measuring project results
to ensure that the project deliverables meet quality standards and
requirements. - Example:
In a construction project, quality control would involve inspecting
completed work to ensure it meets the specified design and regulatory
standards.
R
- Risk:
An uncertain event or condition that, if it occurs, has an effect on at
least one project objective (such as scope, schedule, cost, or quality). - Example:
A supplier failure could be a risk that may impact the project schedule. - Risk
Management Plan: A document that defines how risk management
activities will be structured and performed throughout the project,
including risk identification, assessment, and mitigation strategies. - Example:
The risk management plan might include a list of risks with their
likelihood and impact, as well as detailed strategies for mitigating
them. - Risk
Register: A tool used to document identified risks, their causes,
impacts, and the responses planned to manage them. - Example:
A risk register for a software development project might list risks such
as technology changes, lack of skilled resources, and customer changes to
requirements.
S
- Schedule
Management Plan: A document that defines how the project schedule will
be managed, including the scheduling methodology, tools, and techniques to
be used. It also includes the criteria for schedule performance
evaluation. - Example:
The schedule management plan might specify that project progress will be
tracked using Gantt charts and that any schedule changes must be approved
by the project sponsor. - Scope
Creep: The uncontrolled expansion of project scope without adjustments
to time, cost, and resources. It typically occurs when new features or
requirements are added to the project after it has started without proper
evaluation. - Example:
If the client requests additional features for a software application
after the project scope has been defined, without considering the impact
on the timeline or budget, this can lead to scope creep. - Scope
Management Plan: A document that defines how the scope will be
defined, validated, and controlled throughout the project. It helps
prevent scope creep and ensures that all project work is included. - Example:
The scope management plan might outline the process for approving scope
changes and setting up formal procedures to manage scope boundaries. - SMART
Criteria: A method used to set project objectives that are Specific,
Measurable, Achievable, Relevant, and Time-bound. - Example:
A SMART goal for a project might be, “Complete user training by the
end of Q3 with at least 90% of the users passing a post-training
exam.” - Stakeholder
Register: A document that lists all stakeholders involved in the
project, including their interests, expectations, and influence on the
project. It helps ensure that stakeholders are properly identified and
managed. - Example:
A stakeholder register for a construction project might include
contractors, architects, local government agencies, and the community. - Schedule
Baseline: A version of the project schedule that is approved and used
to measure and monitor project performance. It includes the planned start
and finish dates for project activities and milestones. - Example:
The schedule baseline might indicate that the software development
project will be completed by the end of the year with defined milestones
for key deliverables.
T
- Team
Charter: A document that outlines the expectations, roles, and
responsibilities of the project team. It also defines how the team will
work together, resolve conflicts, and ensure effective communication. - Example:
The team charter for a project might specify that all team members will
meet twice a week to discuss project progress and set expectations for
how issues will be handled. - Tangible
Assets: Physical resources and assets that contribute to the success
of a project, such as materials, equipment, or facilities. - Example:
A construction project might have tangible assets like bricks, cement,
and tools that are essential for completing the work. - Total
Float: The amount of time that a task can be delayed without affecting
the project’s completion date or the start of any dependent tasks. It is
an important concept in project scheduling. - Example:
If a task has a total float of 3 days, it can be delayed by 3 days
without impacting the project’s final delivery date. - Triple
Constraint: A concept in project management that highlights the
relationship between three main project constraints: scope, time, and
cost. These constraints are often referred to as the “iron triangle.” - Example:
If the project scope is expanded, it may require more time or additional
costs to meet the new scope. Any changes in one constraint typically
affect the others.
U
- Ultimate
Goal: The overall aim or the main objective a project is striving to
achieve. It typically aligns with the broader business goals and the
project’s purpose. - Example:
In a software development project, the ultimate goal might be to release
a product that improves the client’s business operations and generates a
certain return on investment. - Urgency:
Refers to the need to act quickly to address specific project issues or
objectives. It can apply to project timelines, the resolution of issues,
or the fulfillment of stakeholder needs. - Example:
If a critical bug is discovered in a software project that could delay
the project, there may be a sense of urgency to resolve the issue
quickly.
V
- Value
Stream Mapping: A lean management technique that analyzes the flow of
materials and information through the project lifecycle to identify areas
of waste and inefficiency. - Example:
In a manufacturing project, value stream mapping might be used to
identify bottlenecks in the production process where resources are
underutilized or steps could be eliminated to improve overall efficiency. - Variance
Analysis: A technique used to analyze the differences between the
planned performance and the actual performance of a project. It helps in
identifying the cause of any deviations. - Example:
If a project is running over budget, variance analysis might show that
resource costs exceeded expectations or that additional tasks were added
to the scope without proper approval.
W
- Work
Breakdown Structure (WBS): A hierarchical decomposition of the total
project scope into smaller, more manageable components called work
packages. It helps in defining and organizing project work. - Example:
For a construction project, the WBS might break down tasks into
categories like foundation, framing, roofing, electrical work, and
finishing. - Work
Performance Data: The raw data collected during project execution,
including information about the progress of tasks, resource utilization,
and quality control results. It is used as input for performance analysis. - Example:
Data such as the percentage of tasks completed, hours worked by each team
member, and the number of defects identified in the product are
considered work performance data. - Work
Performance Information: The analysis of work performance data that
provides insights into how the project is progressing. It includes the
status of project deliverables and any variances from the project plan. - Example:
A report generated for stakeholders that shows the completion status of
tasks, budget usage, and progress compared to the baseline schedule.
X
- X-Y-Z
Chart: A tool used in project management to analyze and display
relationships between project variables and their impact on the project’s
overall success. It can help identify cause-and-effect relationships. - Example:
A project team might use an X-Y-Z chart to analyze how increasing the
number of resources impacts project completion time.
Y
- Yield
Management: A pricing strategy often used in project management for
managing variable pricing or resources to maximize project profitability. - Example:
In a project where resource costs fluctuate, yield management could
involve adjusting resource allocation or pricing strategies to optimize
project profitability.
Z
- Zero
Defects: A quality management concept that aims to achieve the perfect
delivery of project outcomes without any defects or errors.
Example: A
construction project might have a zero-defects policy, which ensures that all work
is completed to the highest standards and that any minor issues are immediately
addressed.
