Digital Highway PMC Dashboard

Digital Highway PMC Dashboard 

Nagpur – Kalmeshwar Highway Construction Dashboard

body {
font-family: ‘Inter’, sans-serif;
background-color: #f3f4f6; /* Light gray background */
}
.card {
background-color: #ffffff;
border-radius: 0.75rem; /* Rounded corners */
box-shadow: 0 4px 6px -1px rgba(0, 0, 0, 0.1), 0 2px 4px -1px rgba(0, 0, 0, 0.06);
padding: 1.5rem;
}
.progress-bar-container {
background-color: #e5e7eb; /* Light gray for the track */
border-radius: 0.5rem;
height: 1.5rem;
overflow: hidden;
}
.progress-bar {
background-color: #22c55e; /* Green for progress */
height: 100%;
border-radius: 0.5rem;
width: 0%; /* Initial width */
transition: width 0.5s ease-in-out;
}
.kanban-column {
background-color: #f9fafb; /* Lighter background for columns */
border-radius: 0.5rem;
padding: 1rem;
min-height: 150px; /* Ensure columns have some height */
}
.kanban-item {
background-color: #ffffff;
border-radius: 0.5rem;
padding: 0.75rem;
margin-bottom: 0.75rem;
box-shadow: 0 1px 2px 0 rgba(0, 0, 0, 0.05);
}
.graph-container {
width: 100%;
overflow-x: auto; /* Allows horizontal scrolling if graph is wide */
padding-bottom: 1rem; /* Space for potential scrollbar */
}
.earned-value-graph svg {
display: block;
margin: auto;
border: 1px solid #e5e7eb;
border-radius: 0.5rem;
background-color: #fcfcfc;
}
.graph-legend span {
display: inline-flex;
align-items: center;
margin-right: 1rem;
font-size: 0.9rem;
color: #4b5563;
}
.graph-legend span::before {
content: ”;
width: 1.25rem;
height: 0.25rem;
border-radius: 9999px; /* Pill shape */
margin-right: 0.5rem;
display: inline-block;
}
.legend-pv::before { background-color: #3b82f6; } /* Blue */
.legend-ev::before { background-color: #22c55e; } /* Green */
.legend-ac::before { background-color: #ef4444; } /* Red */

Nagpur – Kalmeshwar Highway Construction

Digital PMC Project Dashboard (19 km)

Created by Parag Pal

Project Overview

Location: Nagpur – Kalmeshwar, India

Length: 19 km

Type: Highway Construction

Status: Under Construction

Key Milestones

  • Land Acquisition: Completed
  • Initial Survey & Design: Completed
  • Earthwork & Grading: In Progress
  • Pavement Laying: Upcoming
  • Bridge & Culvert Construction: Upcoming

Project Stakeholders

Main Contractor: ABC Construction Pvt. Ltd.

Project Manager: Mr. Rajesh Kumar

PMC (Project Management Consultant): Global Infra Solutions

PMC Contact: pmc.nagpur@example.com

Project Timeline & Performance

Start Date: January 1, 2024

Planned End Date: December 31, 2025

Current Phase: Construction Phase 1

Earned Value Trend

Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)

Start M2 M3 M4 M5 M6

High Low

Overall Progress

45% Completed

Segment Progress

Segment 1 (0-5 km): 70%

Segment 2 (5-12 km): 40%

Segment 3 (12-19 km): 15%

Financials & Resources

Allocated Budget: INR 500 Crores

Expended Budget: INR 225 Crores (45% of total)

Remaining Budget: INR 275 Crores

Workforce: 350 On-site Personnel

Equipment Deployed: 25 Heavy Machinery Units

Earned Value Analysis (EVA)

Planned Value (PV):
INR 250 Crores
Earned Value (EV):
INR 225 Crores
Actual Cost (AC):
INR 200 Crores

Cost Variance (CV): INR 25 Crores (Favorable)

Schedule Variance (SV): INR -25 Crores (Unfavorable)

Cost Performance Index (CPI): 1.125

Schedule Performance Index (SPI): 0.9

Cash Flow

Total Planned Inflow:
INR 500 Crores
Total Actual Inflow:
INR 225 Crores
Total Planned Outflow:
INR 250 Crores
Total Actual Outflow:
INR 200 Crores

Net Cash Position (Current): INR 25 Crores

(Actual Inflow – Actual Outflow)

Kanban Board

To Do

Procure asphalt for Segment 2

Due: July 15, 2025

Finalize bridge design for Culvert 3

Due: July 20, 2025

In Progress

Earthwork & Grading – Segment 2

Started: June 20, 2025

Quality check on initial pavement layer

Started: July 5, 2025

Done

Land acquisition completed

Completed: May 10, 2025

Initial survey and design approval

Completed: April 1, 2025

Material Reconciliation

Cement (Tons)
Planned:
10,000
Received:
4,500
Consumed:
4,000
Balance:
500
Steel (Tons)
Planned:
5,000
Received:
2,000
Consumed:
1,800
Balance:
200

Resource & Cost Forecasting

Estimate To Complete (ETC):
INR 275 Crores
Estimate At Completion (EAC):
INR 475 Crores

Man-Month Estimates

Planned Man-Months: 8,000

Actual Man-Months (to date): 3,500

EAC Man-Months: 7,500

Latest Updates

  • June 28, 2025: Completed 70% of earthwork in Segment 1.
  • June 15, 2025: Mobilization of additional heavy machinery for Segment 2.
  • May 30, 2025: Successful completion of initial environmental impact assessment.

Contact & More Info

For more details, please contact the Project Management Team.

Email: info@example.com

// JavaScript to dynamically update progress bar (example)
document.addEventListener(‘DOMContentLoaded’, function() {
const overallProgressBar = document.getElementById(‘overallProgressBar’);
const overallProgressText = document.getElementById(‘overallProgressText’);

// Simulate progress update (you can replace this with actual data fetching)
let currentProgress = 45; // Initial value
// For demonstration, let’s say progress increases over time
// setInterval(() => {
// if (currentProgress 100) currentProgress = 100;
// overallProgressBar.style.width = currentProgress + ‘%’;
// overallProgressText.textContent = currentProgress + ‘% Completed’;
// }
// }, 2000); // Update every 2 seconds
});

Leave a Reply

Your email address will not be published. Required fields are marked *