Highway DPR – Daily Progress Report – Excel format free download

Highway DPR – Daily Progress Report

Infrastructure development is often seen as a long-term endeavor, but its success lies in the daily discipline of execution. Every meter of road laid, every ton of asphalt poured, and every hour of labor invested contributes to the larger vision of connectivity and progress. Today, I’m sharing a snapshot from the NH-44 Highway Upgrade Project—a daily progress report that reflects not just numbers, but the operational rigor behind them.

Highway DPR – Daily Progress Report – Excel format free download

🌤️ Project Overview

  • Project Name: NH-44 Upgrade
  • Location: KM 150 to KM 180
  • Report No: DPR-2024-125
  • Date: July 17, 2025
  • Weather Conditions: Sunny, Max Temperature: 38°C

Despite the scorching heat, the site team maintained momentum, delivering measurable progress across multiple activities. This report captures the essence of what it takes to keep a large-scale infrastructure project on track—day by day.

🚧 Work Progress Summary

The day’s activities were spread across excavation, sub-base preparation, macadam laying, asphalt paving, and structural work. Here’s a breakdown:

Activity Chainage Planned Achieved Cumulative
Earthwork (Excavation) 152+000 to 155+500 1,500 m³ 1,650 m³ 45,000 m³
Granular Sub-Base (GSB) 152+100 to 152+400 1,200 m³ 1,200 m³ 32,000 m³
Wet Mix Macadam (WMM) 152+400 to 155+800 750 m³ 750 m³ 25,000 m³
Asphalt Concrete (BC) 150+000 to 151+300 400 Ton 410 Ton 8,500 Ton
Culvert Construction (Box) 153+750 1 Nos 1 Nos 5 Nos
Road Markings 150+000 to 151+000 1,000 m 1,000 m 1,000 m

The team exceeded expectations in excavation and asphalt laying, demonstrating strong coordination and resource utilization.

👷‍♂️ Manpower & Machinery Deployment

Manpower Utilization

Role Planned Actual
Project Manager 1 1
Site Engineers 3 4
Supervisors 5 5
Surveyors 2 2
Skilled Laborers 40 38
Unskilled Laborers 80 85

The slight increase in unskilled labor helped maintain pace in manual tasks, while the engineering team ensured technical oversight.

Machinery Utilization

Equipment Planned (Hrs) Actual (Hrs)
Excavators 16 18
Dump Trucks 60 65
Graders 8 8
Rollers 16 14
Asphalt Pavers 8 7
Water Tankers 8 8

Extended excavator and dump truck hours enabled faster earthwork, while a minor roller breakdown slightly impacted WMM laying.

🧱 Material Consumption

Material Opening Stock Received Consumed Closing Stock
Aggregate (20mm) 5,000 m³ 1,500 m³ 1,100 m³ 5,400 m³
Aggregate (10mm) 3,500 m³ 1,000 m³ 800 m³ 3,700 m³
Bitumen VG-30 800 Ton 200 Ton 150 Ton 850 Ton
Cement 1,200 Bags 0 50 Bags 1,150 Bags
Steel Reinforcement 250 Ton 20 Ton 15 Ton 255 Ton

Material flow was smooth, with adequate reserves maintained for uninterrupted operations.

To download the excel format, click here.

Leave a Reply

Your email address will not be published. Required fields are marked *