Key Mindsets, TTOS and Questions with Solutions for Task 11: Close the Project or Phase to Crack PMP exam

Introduction

This post help you to understand the Key Mindsets, TTOS and Questions with Solutions for Task 11: Close the Project or Phase to Crack PMP exam in 1 month. I am PMP certified and project management expert and having vast experience. The main intention of this post is to help PMP aspirants to crack the EXAM and prepare them for the PMP exams. 

The step by step key Mindsets, TTOS and Situational questions with Answers for PMP exam are explain in this post.

Task 11: Close the Project or Phase it deals with below objectives and you will get questions based on these factors in PMP exam.

  • Successfully close the project or phase, ensuring all deliverables are met and final documentation is completed.
  • Includes conducting post-project reviews, capturing lessons learned, and ensuring stakeholder satisfaction.

Task 11: Close the Project or Phase

 

Mindset

 

1.    Complete the Project Deliverables: Ensure that all project deliverables are completed, accepted by the stakeholders, and meet the defined requirements.

2.    Verify Completion of All Project Requirements: Double-check that all aspects of the project or phase are finalized, including contractual obligations, quality standards, and scope.

3.    Review and Finalize Documentation: Ensure that all documentation, including contracts, project plans, reports, and other project artifacts, are completed and stored for future reference.

4.    Conduct Post-Project Reviews: Facilitate a post-project review meeting to gather feedback, assess performance, and identify areas for improvement.

5.    Capture and Document Lessons Learned: Gather insights from all team members and stakeholders, documenting lessons learned and recommendations for future projects.

6.    Obtain Stakeholder Approval: Confirm that all stakeholders are satisfied with the deliverables and the project has met its objectives before formally closing.

7.    Release Project Resources: Release project resources, including human resources, materials, and equipment, and reallocate them as needed.

8.    Close Contracts: Ensure that all contracts, both internal and external, are completed, closed, and all payments are processed.

9.    Prepare for Handover: Ensure that all final project deliverables are handed over to the client or appropriate parties for ongoing operation or maintenance.

10.  Communicate Closure: Communicate the formal closure of the project or phase to all stakeholders, summarizing achievements and next steps.

 

Key TTOS

 

1.    Outputs:

·         Final project report

·         Lessons learned documentation

·         Formal project acceptance

·         Finalized project documents

·         Post-project review

·         Resource release documentation

·         Contract closure

·         Handover documents

2.    Tools and Techniques:

·         Expert Judgment: Used to evaluate project closure and ensure all deliverables and contractual obligations are completed.

·         Project Management Information Systems (PMIS): For tracking documentation, deliverables, and status during the closing phase.

·         Meetings: To conduct project closure meetings, review final deliverables, gather lessons learned, and ensure stakeholder satisfaction.

·         Data Analysis: Used to analyze project performance and identify lessons learned.

·         Lessons Learned Repository: A central place to store project lessons learned and best practices.

·         Quality Audits: To ensure all project deliverables meet the required quality standards.

 

Question

 

Question 1

You are nearing the end of a project. Some stakeholders are still dissatisfied with the project deliverables. What is the best course of action for the project manager to take?

A) Ignore the stakeholders’ concerns and proceed to close the project.
B) Engage with the dissatisfied stakeholders to understand their concerns, and work on resolving the issues before project closure.
C) Close the project immediately to avoid further delays.
D) Close the project and inform the stakeholders that any concerns will be handled after the closure.

Correct Answer: B) Engage with the dissatisfied stakeholders to understand their concerns, and work on resolving the issues before project closure.
Explanation: Engaging with stakeholders and addressing their concerns ensures their satisfaction, which is critical before closing the project.
Mindset Applied: Ensuring that all stakeholder concerns are addressed before closure fosters stronger relationships and project success.


Question 2

During the project closing phase, the team identifies some incomplete documentation. What should the project manager do?

A) Proceed with project closure without completing the documentation.
B) Complete the documentation before finalizing the project closure to ensure proper records are maintained.
C) Inform the sponsor about the incomplete documentation and ask them to handle it.
D) Close the project and make a note about the incomplete documentation for future reference.

Correct Answer: B) Complete the documentation before finalizing the project closure to ensure proper records are maintained.
Explanation: Incomplete documentation can lead to issues in future audits or reviews, so it’s essential to ensure everything is finalized before closure.
Mindset Applied: Proper documentation is vital for project history, compliance, and future reference, ensuring that nothing is overlooked.


Question 3

What should the project manager do when a lesson learned is identified late in the project, just before closing?

A) Ignore the lesson learned because it’s too late in the project.
B) Document the lesson learned and include it in the project’s closing report.
C) Keep the lesson learned only for internal team use and avoid sharing it with stakeholders.
D) Postpone project closure until the lesson learned is fully analyzed.

Correct Answer: B) Document the lesson learned and include it in the project’s closing report.
Explanation: Capturing lessons learned is essential, even if identified late in the project, as they can improve future projects.
Mindset Applied: Reflecting on lessons learned and sharing them strengthens future project management practices and improves team performance.


Question 4

A client is not satisfied with the final deliverables of a project and refuses to accept them. What should the project manager do?

A) Close the project anyway, regardless of client satisfaction.
B) Review the client's concerns, identify any gaps, and resolve the issues before proceeding with closure.
C) Ignore the client’s feedback and proceed with project closure.
D) Notify the project sponsor and close the project without client acceptance.

Correct Answer: B) Review the client's concerns, identify any gaps, and resolve the issues before proceeding with closure.
Explanation: Client satisfaction is key to the success of the project, and the project manager must ensure all issues are addressed before closure.
Mindset Applied: Actively managing stakeholder expectations and addressing concerns ensures successful project closure and a positive relationship with the client.


Question 5

The project has successfully completed all deliverables, but the project sponsor requests additional work just before project closure. What should the project manager do?

A) Agree to the additional work and extend the project.
B) Assess the impact of the additional work on the project’s scope, schedule, and budget and initiate a change control process if needed.
C) Refuse the request and close the project immediately.
D) Complete the additional work without any formal evaluation.

Correct Answer: B) Assess the impact of the additional work on the project’s scope, schedule, and budget and initiate a change control process if needed.
Explanation: Any additional work should be evaluated to assess its impact on the project before proceeding. The change control process should be followed to ensure proper management of changes.
Mindset Applied: Changes requested at closure must be carefully evaluated, as they could significantly affect the project’s success.


Question 6

You are closing a project and conducting a post-project review. What should be the primary focus of this review?

A) Only discuss the budget and schedule.
B) Analyze both positive outcomes and challenges, gather feedback from the team, and document lessons learned.
C) Focus exclusively on the team’s performance.
D) Review only the project deliverables.

Correct Answer: B) Analyze both positive outcomes and challenges, gather feedback from the team, and document lessons learned.
Explanation: A comprehensive review helps capture insights that improve future projects and recognizes what went well and where improvements are needed.
Mindset Applied: A holistic post-project review ensures continuous improvement by capturing valuable lessons and acknowledging the team’s achievements.


Question 7

A project’s final deliverable has been handed over, and the client is satisfied. What should the project manager do next?

A) Close the project and send the final report to the client without further review.
B) Complete the final project documentation, ensure all financials are settled, and formally close the project with stakeholders.
C) Distribute the project completion report to all team members and wait for their feedback.
D) Focus on the next project and leave the closure process for later.

Correct Answer: B) Complete the final project documentation, ensure all financials are settled, and formally close the project with stakeholders.
Explanation: Formal project closure ensures that all elements, including financials, documentation, and stakeholder satisfaction, are complete before closing the project.
Mindset Applied: Ensuring all aspects of the project are properly closed out is critical to avoid future misunderstandings or issues.


Question 8

The project has concluded, but there are still some contractual obligations pending. What should the project manager do?

A) Close the project immediately and leave the contractual obligations unresolved.
B) Resolve all contractual obligations and ensure the contracts are closed before formally closing the project.
C) Inform the sponsor of the pending obligations and proceed with project closure.
D) Ignore the obligations and close the project as planned.

Correct Answer: B) Resolve all contractual obligations and ensure the contracts are closed before formally closing the project.
Explanation: All contractual obligations should be fulfilled before the project is closed to avoid potential legal or financial issues.
Mindset Applied: Meeting contractual obligations is a critical part of responsible project management and closure.


Question 9

You are closing a project, and the sponsor requests a final status report that includes lessons learned and performance reviews. How should you proceed?

A) Provide a status report without including lessons learned or performance reviews.
B) Create a comprehensive status report that includes the final project performance, lessons learned, and other relevant documentation.
C) Submit an incomplete report and mention that the remaining information will be provided later.
D) Focus solely on the financials and avoid discussing performance reviews or lessons learned.

Correct Answer: B) Create a comprehensive status report that includes the final project performance, lessons learned, and other relevant documentation.
Explanation: A complete and detailed report provides valuable information for stakeholders and captures lessons that could benefit future projects.
Mindset Applied: Ensuring that all relevant details are documented and shared helps in both project closure and future improvements.


Question 10

You are conducting a post-project review with the team. What is the primary benefit of holding this review?

A) To assign blame for any project failures.
B) To identify lessons learned and determine what can be improved for future projects.
C) To focus solely on the positive aspects of the project.
D) To ensure the team is aware of their shortcomings and improve their performance.

Correct Answer: B) To identify lessons learned and determine what can be improved for future projects.
Explanation: The main goal of a post-project review is to capture insights that will improve future project management and team performance.
Mindset Applied: A forward-thinking mindset ensures continuous improvement by learning from both successes and challenges.


Conclusion

The Close the Project or Phase process is crucial in ensuring a smooth transition from project execution to closure. Properly closing a project involves completing deliverables, reviewing performance, capturing lessons learned, and ensuring stakeholder satisfaction. By thoroughly documenting all aspects of the project and engaging with the team and stakeholders, the project manager ensures the project is concluded successfully, with all elements aligned for future improvements.


Question 11

A client has requested that a post-project review be conducted with all stakeholders after the project is completed. How should the project manager handle this request?

A) Deny the request because the project is officially closed.
B) Organize a post-project review with stakeholders and ensure that lessons learned are discussed.
C) Send a final report to the stakeholders without involving them in a meeting.
D) Postpone the review until the team has completed other ongoing tasks.

Correct Answer: B) Organize a post-project review with stakeholders and ensure that lessons learned are discussed.
Explanation: A post-project review provides valuable insights and fosters continuous improvement. It’s essential to involve stakeholders in this process.
Mindset Applied: Engaging stakeholders in the review process ensures transparency and provides opportunities for learning and growth for future projects.


Question 12

What is the best way for a project manager to ensure that all stakeholders are satisfied during project closure?

A) Ignore stakeholder feedback and finalize the project closure.
B) Hold regular status meetings until the last day of the project.
C) Seek stakeholder feedback, address concerns, and ensure all expectations are met before officially closing the project.
D) Assume that stakeholders are satisfied and close the project without additional communication.

Correct Answer: C) Seek stakeholder feedback, address concerns, and ensure all expectations are met before officially closing the project.
Explanation: Proactively engaging with stakeholders and addressing concerns ensures their satisfaction and smooth project closure.
Mindset Applied: Prioritizing stakeholder satisfaction throughout the closing phase builds positive relationships and trust for future collaborations.


Question 13

You’re closing a project, and during the final review, a major defect is discovered in the final deliverables. What should the project manager do?

A) Close the project without addressing the defect.
B) Inform the client and initiate corrective actions before completing the closure process.
C) Delay the closure process and investigate the cause of the defect later.
D) Inform the sponsor that the project can be closed, and the defect will be dealt with at a later time.

Correct Answer: B) Inform the client and initiate corrective actions before completing the closure process.
Explanation: It is crucial to address any issues or defects before closing the project to maintain quality standards and stakeholder satisfaction.
Mindset Applied: Taking swift corrective action ensures that the project meets the required quality standards and that client expectations are met before closure.


Question 14

During the closure phase, the project manager realizes that some resources are still allocated to the project but are not needed anymore. What should the project manager do?

A) Ignore the unnecessary resources and leave them allocated.
B) Release the resources immediately and ensure they are reassigned to other projects or tasks.
C) Continue paying for the resources and keep them on standby until the project is closed.
D) Leave the resources allocated but notify the project sponsor.

Correct Answer: B) Release the resources immediately and ensure they are reassigned to other projects or tasks.
Explanation: Efficiently reallocating or releasing resources ensures that costs are minimized and that resources can be utilized elsewhere.
Mindset Applied: Proper resource management during closure prevents unnecessary costs and fosters effective utilization of team members and materials.


Question 15

The project team has completed their tasks, and the project is about to close. What key document should be completed before officially closing the project?

A) The project initiation document.
B) The change request document.
C) The final project report, which includes project performance and lessons learned.
D) The project risk register.

Correct Answer: C) The final project report, which includes project performance and lessons learned.
Explanation: The final report documents the project’s outcomes, lessons learned, and performance metrics, which are crucial for closing the project.
Mindset Applied: Documenting performance and lessons learned ensures that all stakeholders have a comprehensive view of the project and that valuable knowledge is captured for future use.


Question 16

During project closure, the project manager finds that a small number of project tasks were not completed on time. How should the project manager proceed?

A) Ignore the missed tasks and proceed with the closure.
B) Report the missed tasks as open items and leave them unresolved in the final report.
C) Identify the reasons for the missed tasks and ensure they are addressed before closing.
D) Close the project and accept the incomplete tasks as final.

Correct Answer: C) Identify the reasons for the missed tasks and ensure they are addressed before closing.
Explanation: It’s important to identify the causes of incomplete tasks and address them to ensure that all deliverables are met before closure.
Mindset Applied: Addressing incomplete tasks and understanding their causes helps in maintaining quality and ensuring a successful project closure.


Question 17

As the project manager, you notice that some project documents are missing during the project closure process. What is the best course of action?

A) Close the project and leave the missing documents unresolved.
B) Attempt to retrieve or recreate the missing documents before finalizing the closure.
C) Ignore the missing documents as they are not critical.
D) Blame the team members for losing the documents and close the project.

Correct Answer: B) Attempt to retrieve or recreate the missing documents before finalizing the closure.
Explanation: All necessary project documentation must be completed and stored for future reference and compliance purposes.
Mindset Applied: Ensuring that all project documentation is complete before closure ensures proper record-keeping and legal compliance.


Question 18

The project team is being disbanded after the project’s completion. What should the project manager ensure is done for the team?

A) Only send a thank-you email to the team.
B) Provide the team with feedback, recognize achievements, and discuss any lessons learned.
C) Disband the team without further communication.
D) Wait until the next project starts before engaging with the team.

Correct Answer: B) Provide the team with feedback, recognize achievements, and discuss any lessons learned.
Explanation: Providing feedback and recognizing team members’ contributions is essential for team morale and future collaboration.
Mindset Applied: Recognizing achievements and providing feedback helps maintain positive relationships with team members and encourages their continued growth and engagement.


Question 19

A key stakeholder asks the project manager for a summary of the project’s key performance indicators (KPIs) during closure. What should the project manager do?

A) Provide a vague summary of the KPIs.
B) Present a detailed summary of the KPIs along with explanations of how they were achieved or missed.
C) Only provide financial performance metrics.
D) Ignore the request as the project is now closed.

Correct Answer: B) Present a detailed summary of the KPIs along with explanations of how they were achieved or missed.
Explanation: A detailed summary of KPIs provides stakeholders with transparency into the project’s performance and highlights areas of success or improvement.
Mindset Applied: Transparency during closure builds trust and provides stakeholders with clear insights into the project’s results.


Question 20

After completing the project and ensuring all deliverables have been met, you realize there is an opportunity to optimize project closure. What should the project manager do?

A) Complete the closure process without making changes.
B) Analyze the current closure process, identify areas for improvement, and suggest better practices for future projects.
C) Rush through the closure to move on to the next project.
D) Leave the optimization for the next project manager.

Correct Answer: B) Analyze the current closure process, identify areas for improvement, and suggest better practices for future projects.
Explanation: Identifying opportunities for improvement during closure allows the team to refine the process and improve future project management practices.
Mindset Applied: Continually improving processes ensures more efficient project management and better results in future endeavors.