Change Order letter form - Free download Word format

In today Construction world, the construction is on high demand but the management of the Construction practices are not upto the mark. To manage the Good practices for the "Change order management" every civil engineer should follow the "Change order letter form" along with the Change order.



The Change order modifications to the original scope of work are inevitable. Whether due to unforeseen conditions, client requests, or necessary adjustments, change orders play a crucial role in managing projects effectively. One essential tool for documenting these modifications is the Change Order Letter Form.

Let's dive into the details of a specific change order letter form for a project named "ABC" managed by Civilnotes Ltd., with XYZ.LTD as the employer. 

Watch the below video to understand the Importance of Change order letter form in detail from Parag Pal.


Project Information

The change order letter form for this project includes vital details:

  • Project: ABC

  • Employer: XYZ.LTD

  • Contractor: Civilnotes Ltd.

Change Order Details

This section outlines the specifics of the change order:

  • Change Order No.: 1

  • From: Civilnotes Ltd.

  • To: XYZ.LTD

Reference

The form specifies the changes made to the contract documents:

  • Highway Machines: Additional machines required for the project.

  • Extra Labour: Additional manpower for cleaning tasks.

  • Water Pump: New equipment not included in the original contract.

Change Order Justification

The justification explains why these changes are necessary:

  • The items listed were not part of the original contract, and some existing resources are inadequate to complete the work effectively.

Change to Contract Price

The financial impact of the change order is detailed as follows:

  • Original Contract Price: Rs. 50,00,000

  • Current Project Price: As adjusted by previous change orders: NA

  • Increase Due to Change Order: Rs. 1,00,000

  • New Project Price: Rs. 51,00,000

Change to Contract Time

The form also addresses the impact on the project timeline:

  • Time Increase: 30 Days

  • New Completion Date: 30-12-2024

Distribution

The change order letter form specifies distribution:

  • Original to Contractor

  • cc: Person 1

Ordered by Civilnotes Ltd.

This section includes the signature and date by Civilnotes Ltd., authorizing the change order.

Importance of a Change Order Letter Form

Utilizing a change order letter form ensures transparency and accountability in construction projects. It helps project managers:

  • Track Changes: Documenting every change ensures all stakeholders are aware of modifications and their impacts.

  • Manage Budget: Monitoring cost adjustments helps prevent budget overruns.

  • Adjust Timelines: Keeping a record of time extensions ensures projects stay on track.

Download the change order letter form in WORD: Change order letter

Conclusion

A well-documented change order letter form is indispensable for successful project management in construction. By detailing every modification, its justification, and its impact on cost and time, project managers can navigate the complexities of construction work efficiently. Implementing a change order letter form not only enhances transparency but also ensures that all parties are on the same page, ultimately leading to the successful completion of the project.